Details

  • Mecca-Medina rail link: Spanish firms reach deal with Saudi

    *Consortium building the Mecca-Medina rail link reaches prelim deal with Saudi

    *Deal has seen setbacks due to payments dispute with KSA government

    *Construction period extended by 14 months from original end-date

     
     

    A Spanish consortium that is building a high-speed rail link between Mecca and Medina, has reached a preliminary deal with Saudi Arabia to finalise the works after a series of delays and setbacks, Spain’s public works ministry said on Friday.

    Payments dispute

    The Al Shoula consortium, comprising 12 Spanish companies including OHL and Indra, as well as two Saudi firms, had become embroiled in a dispute over payments with the Saudi government.

    The consortium’s contract to construct and maintain the Haramain railway is valued at €6.7 billion ($7.11bn).

    “This preliminary deal resolves the problems that arose on both sides during the process, clearing the way for the works to be finalised,” the Spanish government said in a statement.

    Ratification pending

    The Saudi government still has to ratify the agreement, a spokesman for the consortium said, but it would extend the construction period until March 2018, 14 months later than originally planned.

    Under the agreement the state-owned Saudi Railways Organization is to pay the consortium ‎€150 million in compensation for additional costs on the project.

    Courtesy AMEinfo



Share on facebook
LinkedIn
}